Type IL Cement: What General Contractors Need to Know About Finishing, Curing and Flooring

Type IL cement is now the default in U.S. concrete, and it changes what happens to the floor installed on top of it. The concrete is sound. The risk is in how the slab is finished and cured, decisions made on pour day by trades that leave before the flooring arrives.

The short version:

  • Finish the slab open: a soft steel trowel, never a hard trowel or burnish, and no densifier where flooring goes.
  • Choose the cure before the pour, and get the flooring adhesive maker's written approval of it.
  • Test before flooring goes down (RH, surface pH, hardness, absorption) against the adhesive maker's limits, not Type I/II rules of thumb.

1. What changed in the cement

Type IL (portland-limestone cement, ASTM C595) replaces 5–15% of the clinker with raw limestone, ground finer than the cement around it. ASTM added it in 2012, and by June 2023 it outsold ordinary portland. It meets the same strength, set and soundness requirements as Type I/II (ASTM C150), and all 50 states approve it for DOT work. What the cement spec never evaluated is how the top few millimeters behave under a flooring adhesive, and most adhesive data sheets were still written for C150 concrete.

Research from the ACI Foundation (April 2026) found Type IL performs comparably to Type I/II when it is properly finished and cured. The rest of this paper is about meeting that condition.

2. What your crews will see on pour day

Type IL gives the finisher less margin. Expect these tendencies, not guarantees:

Field evidence: in a 2024 ACI-ASCC survey of 173 contractors, 77% saw higher water demand and 43% more plastic-shrinkage cracking. In 2023 mockups, six of seven Type IL slabs crusted or tore at evaporation rates as low as 0.03–0.09 lb/ft²/h. In ASCC side-by-side mockups, water-based adhesives bonded weaker over Type IL than over Type I/II.

3. Why it matters at the floor

A Type IL slab can look ready to bond before it is. Every portland slab starts near pH 12.5–13.5; Type IL holds that pH at the surface longer:

  1. Fine limestone packs the paste, so the top few millimeters densify and dry slowly.
  2. Wet pores keep out the CO₂ that would normally carbonate and neutralize the surface.
  3. High surface pH persists, and returns after the surface is sealed and re-wetted.
  4. Low-VOC, water-based adhesives tolerate less alkalinity than the solvent products they replaced, so the bond fails, often a year or more after installation.

A hard-troweled or burnished finish, a densifier, or a film-forming cure closes those same pores further. That is why finishing and curing decide the outcome more than the mix does.

Moisture tests can miss it. ASTM F2170 (RH) and F1869 (MVER) measure moisture, not how long surface alkalinity persists, and their usual limits were set on Type I/II concrete. In the ASCC mockups, Type IL passed moisture tests nearly as well as Type I/II and still bonded weaker. Test surface pH, hardness and absorption too.

4. Finish it open

Finishing is the biggest lever: a closed surface traps water and alkali under the floor.

5. Cure and seal: choose before the pour

Pick the cure before the pour, get the flooring adhesive maker's written approval, and cure at least 7 days (ACI 308); S3 recommends 10 or more for Type IL.

Disclosure: S3 Surface Solutions makes a product in the salt-sequestering category; its data sheet is available on request.

6. What goes wrong, and what it costs

Most Type IL flooring failures trace back to finishing and curing, and every fix after the pour costs more:

Stop and check if you see: a mill cert reading C595/Type IL where C150 was specified; w/c at or above 0.45; no vapor retarder; a chalky surface or Mohs below 5; a water drop that beads instead of soaking in (ASTM F3191); hollow spots or spider cracks; HVAC not running at install; remediation put off "until later."

7. Weather and supply: plan for the season you pour in

The season decides what goes wrong first.

8. Questions to answer before the pour

The general contractor is the only party on site from pour to flooring, so these answers belong in the GC's file before the first truck arrives.

Ask the ready-mix supplier

Ask the concrete contractor

Answer as the GC

Before flooring: test, don't assume

  1. Run HVAC at service conditions for 48 hours.
  2. Test RH per ASTM F2170: 3 tests in the first 1,000 sf, plus 1 per additional 1,000 sf.
  3. Test surface pH (F710), hardness (Mohs 5 or above) and absorption (F3191 water drop).
  4. Judge every reading against the adhesive maker's limits, not a generic 75% RH.

Sources

Education only. The project specifications and the flooring manufacturer's written requirements govern.

Frequently asked questions

Why do floors fail on Type IL concrete slabs?

The concrete is sound; the risk is in how the slab is finished and cured. Type IL holds high surface pH longer, a hard-troweled or burnished finish, densifier or film-forming cure closes the pores further, and low-VOC water-based adhesives tolerate less alkalinity, so the bond can fail a year or more after installation.

How should a Type IL slab be finished where flooring will go?

Finish it open: a soft steel-trowel final finish, troweled only after bleed water clears and never on a crust. Don't hard-trowel or burnish, don't apply densifiers or silicate hardeners, and don't add jobsite water. Mock up in the season you'll pour.

How long should Type IL concrete be cured?

At least 7 days per ACI 308; S3 recommends 10 or more for Type IL. Pick the cure method before the pour and get the flooring adhesive maker's written approval of it.

Which cure methods work under flooring?

Wet cure and curing paper or sheet (ASTM C171) leave no residue. Curing compounds (ASTM C309/C1315) often leave a film that blocks adhesive and need the adhesive maker's written OK or mechanical removal. A spray-on, non-silica, salt-sequestering cure needs a written adhesive compatibility letter.

What does a Type IL flooring failure cost?

Slow dry-down means schedule delay or moisture mitigation, typically $1.50–3.00 per square foot. Adhesive failure, often a year or more after install, means tear-out and reinstall. Delamination, spider cracking and dusty surfaces each need grinding or repair before flooring.

What should be tested before flooring goes down?

After 48 hours of HVAC at service conditions: RH per ASTM F2170 (3 tests in the first 1,000 sf plus 1 per additional 1,000 sf), surface pH (F710), hardness (Mohs 5 or above) and absorption (F3191 water drop), judged against the adhesive maker's limits, not a generic 75% RH.

JA
About the author
Jack Aspenson is CEO of S3 Surface Solutions, which makes substrate preparation and moisture-mitigation products for flooring. Questions about this paper: jack@s3surfaces.com.